FILE - Reactor number 3 and it's cooling tower stands at Georgia Power Co.'s Plant Vogtle nuclear power plant on Jan. 20, 2023, in Waynesboro, Ga. (AP Photo/John Bazemore, File)
ATLANTA — A nuclear power plant in Georgia has begun splitting atoms in one of its two new reactors, Georgia Power said Monday, a key step toward reaching commercial operation at the first new nuclear reactors built from scratch in decades in the United States.
The unit of Atlanta-based Southern Co. said operators reached self-sustaining nuclear fission inside the reactor at Plant Vogtle, southeast of Augusta. That makes the intense heat that will be used to produce steam and spin turbines to generate electricity.
A third and a fourth reactor were approved for construction at Vogtle by the Georgia Public Service Commission in 2009, and the third reactor was supposed to start generating power in 2016. The company now says Unit 3 could begin commercial operation in May or June.
Unit 4 is projected to begin commercial operation sometime between this November and March 2024.
The cost of the third and fourth reactors was originally supposed to be $14 billion. The reactors are now supposed to cost more than $30 billion. That doesn’t include $3.68 billion that original contractor Westinghouse paid to the owners after going bankrupt, which brings total spending to more than $34 billion.
FILE – The reactor vessel in reactor 3 stands at Georgia Power Co.’s Plant Vogtle nuclear power plant on Jan. 20, 2023, in Waynesboro, Ga. (AP Photo/John Bazemore, File)
The latest set of delays at Unit 3 included a pipe part of a critical backup cooling system that was vibrating during startup testing. Construction workers had failed to install supports called for on blueprints. The company has also said it had to repair a slowly dripping valve and diagnose a problem involving water flow through reactor coolant pumps.
Georgia Power said Unit 3 would continue startup testing to show that its cooling system and steam supply system will work at the intense heat and pressure that a nuclear reactor creates. After that, operators are supposed to link the reactor to the electrical grid and gradually raise it to full power.
“We remain focused on safely bringing this unit online, fully addressing any issues and getting it right at every level,” Chris Womack, chairman, president and CEO of Georgia Power, said in a written statement. “Reaching initial criticality is one of the final steps in the startup process and has required tremendous diligence and attention to detail from our teams.”
Georgia Power owns a minority of the two new reactors. The remaining shares are owned by Oglethorpe Power Corp., the Municipal Electric Authority of Georgia and the city of Dalton. Oglethorpe and MEAG would sell power to cooperatives and municipal utilities across Georgia, as well in Jacksonville, Florida, and parts of Alabama and the Florida Panhandle.
Georgia Power’s 2.7 million customers are already paying part of the financing cost, and state regulators have approved a monthly rate increase of $3.78 a month as soon as the third unit begins generating power. The elected Georgia Public Service Commission will decide later who pays for the remainder of the costs.
Vogtle is the only nuclear plant under construction in the United States. Its costs and delays could deter other utilities from building such plants, even though they generate electricity without releasing climate-changing carbon emissions.
CAPE CANAVERAL, Fla. (AP) — The Webb Space Telescope has found no evidence of an atmosphere at one of the seven rocky, Earth-sized planets orbiting a nearby star.
FALMOUTH, MA – The police in Falmouth have identified the victim in an accident involving a car plunging into the ocean on February 20, NBC10 Boston reported.
To purchase a gift subscription, please log out of your account, and purchase the subscription with a new email ID.
On April 2, 2021, we celebrated The National Herald’s 106th Anniversary. Help us maintain our independent journalism and continue serving Hellenism worldwide.
In order to deliver a more personalized, responsive, and improved experience, we use cookies to remember information about how you use this site. By Continuing to access the website, you agree that we will store data in a cookie as outlined in our Privacy Policy.
We use cookies on our site to personalize your experience, bring you the most relevant content, show you the most useful ads, and to help report any issues with our site. You can update your preferences at any time by visiting preferences. By selecting Accept, you consent to our use of cookies. To learn more about how your data is used, visit our cookie policy.
You’re reading 1 of 3 free articles this month. Get unlimited access to The National Herald. or Log In
You’ve reached your limit of free articles for this month. Get unlimited access to the best in independent Greek journalism starting as low as $1/week.